Create / Edit an Activity Status

How to edit existing and create new activity status's

Updated over a week ago

An activity status identifies how far along the activity has progressed. There are several activity statuses available in the stock version of Method:

  • Not Started: Not yet started.

  • Cancelled: Cancelled, but is still saved in Method.

  • Completed: Completed, is still saved in Method, but will no longer appear in Due Now lists.

  • Deferred: Not considered complete, but has been put on hold.

  • In progress: An activity that is ongoing.

  • Waiting on someone else: Waiting on another user, client, or someone else connected to the activity. This status is important to scheduling when using Field Services.

However, the whole point of Method is to tailor your CRM experience to your business practices, so we’ve included an option to create a new activity status.

The following steps will show you how to create and edit activity statuses.

Note: The add and edit screens are laid out the same way, so we will go through how to add a new status. You can edit an existing status by clicking on it and changing the information in the fields.


Creating a Custom Activity Type

  1. On your Method dashboard, click the vertical ellipses ( ) on the Activities App, and select Preferences.

  2. Under Default Activity Status, open the dropdown and click Add / Edit List.

  3. From here, you can choose to edit an existing activity status or create a new one. Click ⊕ New Activity Status.

  4. On the New / Edit Activity Status screen, you will see the following fields:

    • Activity Status*: Select a unique name that best describes the status.

    • Activity Status Type*: this affects what appears in your “due” list. Only activities marked Pending will appear in these lists. Options available are:

      • Pending

      • Completed

      • Cancelled

    • Status Color: The color of your activity when it shows on the activity calendar. This color should be a HTML Hex Code color, for example: #0D71C8. To generate a color, you can use the W3School's color picker website.

    • Cause reminder?: Applying this status means an email reminder will be sent to the assigned user about 15 minutes before the activity is due.

    • Active?: It is best practice not to delete a Status so as not to leave activities with an empty status. It is better to make them inactive instead.

  5. When you’re all done, click Save. This activity status is now available throughout Method.